BHCC - Madeira Terraces Restoration Phase 1 - Main Contractor
Details
- Value
- GBP 11,000,000
- Topic
- Construction work
- Published
- 18 January 2023
- Submission
- 2 March 2023
- Source
- uk:contracts_finder
Tender description
Madeira Terrace is a well-known and much-loved Brighton and Hove Landmark. At 865m long in total it is one of the longest cast-iron structures in the world and an admired piece of Victorian architecture, integral to the Eastern Seafront. It is also a significant Grade 2* listed structure within the rich heritage context of the wider coastal city. Phase 1 of the Madeira Terrace Restoration project encompasses 40nr arches sitting between the Royal Crescent steps and the Shelter Hall / Concord 2. The cast iron structure forms a backbone describing the historic development of the seafront. Addressing the sea and the beach firmly braced against the rising East Cliff wall rising behind. It is a 'backdrop': designed and intended to be used and inhabited by the residents of the city for all manner of events and social occasions; for quiet enjoyment, outdoor exercise and for viewing. The structure is now deemed unsafe and public access has not been possible for a number of years, due its condition. The Phase 1 project includes the following elements of works: • Conservation and repair of the historic cast iron structure. • Conservation and management of the historic Japanese Spindle green wall [dating from 1872], and other planting associated with the Green Wall. • Repairs to the facing of the east cliff-wall (a designated highways structure) to ensure public safety; and re-presentation of its surface to visually unify and present a more attractive backdrop to the restored structure. • Public realm landscaping to both the terrace deck above and the promenade walkway below, including new hard surfacing, soft landscaping and street furniture. • Local improvement to Madeira Drive, via new pedestrian crossing points. • New lighting and servicing infrastructure • Repairs and upgrades to the existing lift mechanism within the Shelter Hall / Concorde 2 building, to allow its continued historic function as the original means of step-free access to the terrace. • A new external public lift
Timeline
- Completed: Tender published18 January 2023Current notice
- Completed: Submission date2 March 2023
About the buyer
Brighton and Hove City Council is a public sector buyer in United Kingdom publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.
Relevant CPV codes
- 45000000 · Construction work
Decision makers
Connect with the people behind this procurement.
| Contact name | Job title | Phone number | Work email |
|---|---|---|---|
| Head of Procurement | +44 •••• •••••• | ••••••••@brighton-and-hove-city-council.gov | |
| Commercial Director | +44 •••• •••••• | ••••••••@brighton-and-hove-city-council.gov | |
| Procurement Manager | +44 •••• •••••• | ••••••••@brighton-and-hove-city-council.gov | |
| Category Lead | +44 •••• •••••• | ••••••••@brighton-and-hove-city-council.gov | |
| Senior Buyer | +44 •••• •••••• | ••••••••@brighton-and-hove-city-council.gov | |
| Contracts Manager | +44 •••• •••••• | ••••••••@brighton-and-hove-city-council.gov |
117 similar open tenders
See more open tenders related to BHCC - Madeira Terraces Restoration Phase 1 - Main Contractor.
- Open tender
Property QUDM
- Open tender
Plumpton Sports Pavilion
- Open tender
Property Works
- Open tender
Provision of Contractor Services
Related topics
Topics related to BHCC - Madeira Terraces Restoration Phase 1 - Main Contractor, ranked by notice volume.
- 11,175£1.0tn
- 26,970£1.7tn
Related buyers
Buyers similar to Brighton and Hove City Council.
- 926£939.2m
- 839£682.3m
- 773£1.7bn
- 737£14.1bn
- 723£150.4m
- 652£1.1bn
- 641£1.4bn
- 555£18.6bn
- 522£2.8bn
- 502£777.8m
Win more public sector contracts
Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.