Expired contract

BHCC - Madeira Terraces Restoration Phase 1 - Main Contractor

Details

Value
GBP 12,500,000
Duration
2 years
Topic
Construction work
Published
2 September 2024

Tender description

Madeira Terrace is a well-known and much-loved Brighton and Hove Landmark. At 865m long in total it is one of the longest cast-iron structures in the world and an admired piece of Victorian architecture, integral to the Eastern Seafront. It is also a significant Grade 2* listed structure within the rich heritage context of the wider coastal city. Phase 1 of the Madeira Terrace Restoration project encompasses 40nr arches sitting between the Royal Crescent steps and the Shelter Hall / Concord 2. The cast iron structure forms a backbone describing the historic development of the seafront. Addressing the sea and the beach firmly braced against the rising East Cliff wall rising behind. It is a 'backdrop': designed and intended to be used and inhabited by the residents of the city for all manner of events and social occasions; for quiet enjoyment, outdoor exercise and for viewing. The structure is now deemed unsafe and public access has not been possible for a number of years, due its condition. The Phase 1 project includes the following elements of works: • Conservation and repair of the historic cast iron structure. • Conservation and management of the historic Japanese Spindle green wall [dating from 1872], and other planting associated with the Green Wall. • Repairs to the facing of the east cliff-wall (a designated highways structure) to ensure public safety; and re-presentation of its surface to visually unify and present a more attractive backdrop to the restored structure. • Public realm landscaping to both the terrace deck above and the promenade walkway below, including new hard surfacing, soft landscaping and street furniture. • Local improvement to Madeira Drive, via new pedestrian crossing points. • New lighting and servicing infrastructure • Repairs and upgrades to the existing lift mechanism within the Shelter Hall / Concorde 2 building, to allow its continued historic function as the original means of step-free access to the terrace. • A new external public lift

Timeline

  1. Completed: Award date1 November 2023
  2. Completed: Award published2 September 2024
    Current notice
  3. Completed: Contract expiry date30 April 2025

About the buyer

Brighton and Hove City Council is a public sector buyer in United Kingdom publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.

Relevant CPV codes

  • 45000000 · Construction work

AI insights

  • Is there a preferred supplier?
  • What are the buyers pain points?
  • What has the buyer previously procured?
  • What are the key requirements?
Sign-up to enrich

Decision makers

Connect with the people behind this procurement.

Contact nameJob titlePhone numberWork email
Head of Procurement+44 •••• ••••••
Commercial Director+44 •••• ••••••
Procurement Manager+44 •••• ••••••
Category Lead+44 •••• ••••••
Senior Buyer+44 •••• ••••••
Contracts Manager+44 •••• ••••••

119 similar open tenders

See more open tenders related to BHCC - Madeira Terraces Restoration Phase 1 - Main Contractor.

Explore all open tenders

Related topics

Topics related to BHCC - Madeira Terraces Restoration Phase 1 - Main Contractor, ranked by notice volume.

View all topics
TopicCountValue
  1. 11,175
    £1.0tn
  2. 26,970
    £1.7tn

Related buyers

Buyers similar to Brighton and Hove City Council.

View all buyers

Win more public sector contracts

Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.