The principal objective of this project is to stop the water ingress into the quarterdeck (battery rooms) area. The works shall consist of taking down the internal plasterboard ceilings in both battery rooms, which will then be replaced with 12.5mm thick Glasroc F Multiboard, and the application of "Tor Elastaseal Z" System to the quarterdeck room. The contractor must submit a works programme, at tender stage with proposed start dates for the sequence of works within this project. It is anticipated that the programme of scheduled works for this project will start in January 2024 for a duration of 8 weeks. A more detailed programme of work will be agreed between the NLB and the successful contractor Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.

Timeline

  1. Completed: Tender published1 December 2023
    Current notice
  2. Completed: Submission date15 December 2023

About the buyer

Northern Lighthouse Board is the General Lighthouse Authority for Scotland and the Isle of Man, a central government agency with its own procurement team. The board maintains 208 lighthouses and 174 buoys along some of the UK's most exposed coastlines. Aviation services are procured jointly with Trinity House across their combined areas. Larger contracts, including its vessel replacement programme, go out to open, competitive tender under UK procurement legislation.

Over the past 5 years, most of Northern Lighthouse Board's contract awards have been in construction work, transport equipment and transport support and travel services.

AI insights

  • Is there a preferred supplier?
  • What are the buyers pain points?
  • What has the buyer previously procured?
  • What are the key requirements?

Decision makers

Connect with the people behind this procurement.

Contact nameJob titlePhone numberWork email
Head of Procurement+44 •••• ••••••
Commercial Director+44 •••• ••••••
Procurement Manager+44 •••• ••••••
Category Lead+44 •••• ••••••
Senior Buyer+44 •••• ••••••
Contracts Manager+44 •••• ••••••

56 similar open tenders

See more open tenders related to Roof.

Explore all open tenders

Related topics

Topics related to GB-Edinburgh: Cape Wrath Lighthouse Roof Repairs, ranked by notice volume.

View all topics
TopicCountValue
  1. 1,010
    £140.0bn
  2. 24,111
    £1.8tn

Finding public sector work shouldn't be hard

Make your next tender search effortless with Stotles. Set up alerts, find decision maker contacts and never miss a good-fit opportunity again.