Painting and protective-coating work of structures
Details
- Buyer
- Transport Scotland
- Supplier(s)
- Spencer
- Value
- GBP 17,890,900
- Duration
- 3 years
- Topic
- Construction work for bridges and tunnels, shafts and subways
- Published
- 26 April 2019
- Source
- TedNotices
Tender description
Transport Scotland wishes to appoint a suitably experienced main contractor to undertake 4 phases of maintenance painting on the external substrates of Erskine Bridge. A single contract will be let with a single contractor responsible for the delivery of all 4 phases of work. Transport Scotland is an agency of the Scottish Government and contracts in the name of and on behalf of the Scottish Ministers. Transport Scotland has identified the requirement to appoint a main contractor to undertake the external painting of the Erskine Bridge. These works are due to commence in spring 2019, for a period of approximately 4 years. The phasing is described below. The main contractor will be procured through a competitive tender procedure, in accordance with the restricted procedure as stated in the Public Contracts (Scotland) Regulations 2015. Due to project complexity, the project will be performed by a single contractor and as such shall not be divided into lots. To be considered for this contract economic operators are required to complete the European Single Procurement Document ESPD in accordance with this Contract Notice. Economic operators shall be evaluated in accordance with the Public Contracts (Scotland) Regulations 2015, on the basis of information they have provided within the ESPD. It is the intention that the project will operate a mandatory Project Bank Account (PBA), a project specific account ring fenced with effective Trust status, for payment of the contractor and his supply chain. The account shall be opened by the Scottish Ministers with The Royal Bank of Scotland under the banking services framework defined at http://www.gov.scot/Topics/Government/Procurement/directory/pscontractcentgovt/BankingServices It is intended that the PBA shall satisfy the minimum requirements for an effectively constituted Trust under Scots law. The use of a PBA by a contractor shall be a contractual requirement. Any sub-contractors for which it is agreed shall not be paid through the PBA shall be entitled to payment according to the prompt payment provisions provided within the contract. Project details There are 4 phases of work. The contract will include a phased completion mechanism. There will be scope for evaluation of the contractor’s performance during each phase of the works. The scope of the works for all phases comprises provision of temporary access systems; removal of the existing paint system; survey and inspection the condition of the existing steelwork; steelwork repairs and strengthening; installation of a new multi-coat paint system in accordance with the specification for highway works. The works will also include the refurbishment of the east and west footway panels and removal of redundant gas mains on the east and west cantilever sections. Phase 1 (spring 2019 — autumn 2019) — West Side Cantilever: Works will include the removal of the west side redundant SGN Gas pipe; removal, refurbishment and reinstatement of the footway panels. Phase 2 (spring 2020 – autumn 2020) – East Side Cantilever: Identical to Phase 1 but applied to the East side including the East side gas main removal and footway panel refurbishment. Phase 3 (spring 2021 – autumn 2021) Lower Sloping Web and Bottom Flange. This phase will include steelwork repairs to the backing flats on the web and bottom flange areas. Phase 4 (spring 2022 – Autumn 2022) – The Bridge Towers: Specialist temporary access systems and traffic management will be required to paint the towers. The contract will only permit continual peak time traffic management when painting the lowest 6 metres of the bridge towers in the central reserve. Special temporary access systems, which can be erected and maintained using off peak traffic management, will be required for all areas above 6 metres high. The works will be let using a fixed price with milestone payments and lane occupation charges contract. The contract will be strongly incentivised to encourage contractors to minimise the amount of disruptive traffic management. TM will not be permitted during the day Monday to Friday. The only exception is in Phase 4 where continual peak time traffic management will be permitted to allow painting of the lowest 6 metres of the bridge towers.
Timeline
- Completed: Award date16 April 2019
- Completed: Award published26 April 2019Current notice
- Completed: Contract expiry date27 September 2022
About the buyer
Transport Scotland is a public sector buyer in United Kingdom publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.
Relevant CPV codes
- 45221000 · Construction work for bridges and tunnels, shafts and subways
- 45221111 · Road bridge construction work
- 45221115 · Construction work for steel bridges
- 45442120 · Painting and protective-coating work of structures
- 45442121 · Painting work of structures
- 45442180 · Repainting work
- 45442190 · Paint-stripping work
Decision makers
Connect with the people behind this procurement.
| Contact name | Job title | Phone number | Work email |
|---|---|---|---|
| Head of Procurement | +44 •••• •••••• | ••••••••@transport-scotland.gov | |
| Commercial Director | +44 •••• •••••• | ••••••••@transport-scotland.gov | |
| Procurement Manager | +44 •••• •••••• | ••••••••@transport-scotland.gov | |
| Category Lead | +44 •••• •••••• | ••••••••@transport-scotland.gov | |
| Senior Buyer | +44 •••• •••••• | ••••••••@transport-scotland.gov | |
| Contracts Manager | +44 •••• •••••• | ••••••••@transport-scotland.gov |
9 similar open tenders
See more open tenders related to Painting and protective-coating work of structures.
- Open tender
YPO - 000881 Ground Maintenance Services
- Open tender
8304-Bridge Painting Qualification System
- Open tender
Construction work
- Open tender
YPO - 000881 Ground Maintenance Services
- Open tender
Construction work
Related topics
Topics related to Painting and protective-coating work of structures, ranked by notice volume.
- 11,175£1.0tn
- 26,969£1.7tn
- 1,689£69.0bn
- 39,910£350.7bn
Related buyers
Buyers similar to Transport Scotland.
- 124£429.4m
- 79£20.0m
- 73£173.1m
- 71£70.8m
- 63£17.4m
- 60£14.8m
- 59£2.7m
- 51£11.3m
- 45£10.3m
- 36£16.6m
Win more public sector contracts
Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.
