Closed tender

AT1385 Buckle Close Electrical Package

Details

Published
20 February 2025
Submission
24 March 2025

Tender description

Electrical Package., the program requires a 6 weeks per floor plus 4 for the penthouses (1st fix), plus 2nd fix timeframes of 4 weeks per floor, will be required to undertake a 40 week programme of works starting July 25 and Completing May26 Please note 1st fix works had already been completed and awarded non-compliantly, but due to water ingress and uncertainty of viability of the installation, the works require procuring compliantly and to the standard and specification required Keywords: New Build, Development, Installation, Electrical

Timeline

  1. Completed: Tender published20 February 2025
    Current notice
  2. Completed: Submission date24 March 2025

About the buyer

Luton Council is a public sector buyer in United Kingdom publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.

AI insights

  • Is there a preferred supplier?
  • What are the buyers pain points?
  • What has the buyer previously procured?
  • What are the key requirements?
Sign-up to enrich

Decision makers

Connect with the people behind this procurement.

Contact nameJob titlePhone numberWork email
Head of Procurement+44 •••• ••••••
Commercial Director+44 •••• ••••••
Procurement Manager+44 •••• ••••••
Category Lead+44 •••• ••••••
Senior Buyer+44 •••• ••••••
Contracts Manager+44 •••• ••••••

Win more public sector contracts

Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.