Grid Connection Costs for Nethermains Solar PV Farm
Details
- Supplier(s)
- Scottish Power Energy Network Holdings
- Value
- GBP 487,730
- Topic
- Other sources of energy supplies and distribution
- Published
- 9 February 2023
Tender description
North Ayrshire Council aim to develop a 7.48MW solar PV farm on the former Nethermains landfill site. A grid connection will be required for Nethermains Solar PV Farm. A grid connection can only be set up by a Distribution Network Operator (DNO). The distribution network operator is responsible for the maintenance and operation of the electric and gas networks up and down the country and in Scotland, unlike England, there is only one DNO. Scottish Power Energy Network (SPEN) are the sole DNO and the only one who can provide a quote to establish a gird connection.
Timeline
- Completed: Award date5 January 2023
- Completed: Award published9 February 2023Current notice
About the buyer
North Ayrshire Council is a public sector buyer in United Kingdom publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.
Relevant CPV codes
- 65400000 · Other sources of energy supplies and distribution
Decision makers
Connect with the people behind this procurement.
| Contact name | Job title | Phone number | Work email |
|---|---|---|---|
| Head of Procurement | +44 •••• •••••• | ••••••••@north-ayrshire-council.gov | |
| Commercial Director | +44 •••• •••••• | ••••••••@north-ayrshire-council.gov | |
| Procurement Manager | +44 •••• •••••• | ••••••••@north-ayrshire-council.gov | |
| Category Lead | +44 •••• •••••• | ••••••••@north-ayrshire-council.gov | |
| Senior Buyer | +44 •••• •••••• | ••••••••@north-ayrshire-council.gov | |
| Contracts Manager | +44 •••• •••••• | ••••••••@north-ayrshire-council.gov |
5 similar open tenders
See more open tenders related to Grid Connection Costs for Nethermains Solar PV Farm.
- Open tender
PfH Energy Supply and Services DPS
- Open tender
Refurbishment work
Related topics
Topics related to Grid Connection Costs for Nethermains Solar PV Farm, ranked by notice volume.
- 3,593£717.5bn
Related buyers
Buyers similar to North Ayrshire Council.
- 198£248.6m
- 183£975.4m
- 180£186.3m
- 155£342.5m
- 155£995.3m
- 151£29.4m
- 137£37.7m
- 127£1.8bn
- 125£2.2bn
- 117£467.2m
Win more public sector contracts
Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.