Bilston and Crescent Rail Replacement
Details
- Supplier(s)
- Haigh Rail Ltd
- Value
- GBP 349,986
- Duration
- 3 months
- Topic
- Railway transport services
- Published
- 14 January 2022
- Source
- uk:contracts_finder
Tender description
Midland Metro runs from Wolverhampton to Birmingham city centre along 21km with 18km of segregated track. There are two areas of rail replacement to be undertaken on the system in the vicinity of the Crescent and Bilston central tram stops, the rail replacement in both areas requires the removal and replacement of the rail within the tram stop area 28 rails at the Crescent and 16 rails at Bilston. The tram stops are constructed on a concrete pad, the track is standard flat bottom 80lb rail R260 type 39E1 18.2 meters per rail length, fixed to concrete mono block sleepers embedded into the primary concrete. The rail sits on rubber pads fixed with pandrol e-clips with nylons against the rail. The rail sits in a protective sleeve with an artificial keep formed from concrete blocks with standard block paving installed across stop area. This opportunity is available via Bravo Solutions and will close on Tuesday 8th June 2021 at 12 noon. Further details of what is required and relating appendices are detailed in the full Invitation to Tender pack. Access to these tender documents can be found on Bravo Solutions and interested suppliers must register to this site to gain access, registration is free. The link to Bravo Solutions website is as follows:- https://wmca.bravosolution.co.uk/web/login.html Please note: • Site visits will take place over two consecutive days on: Tuesday 25th May 2021 and Wednesday 26th May 2021 with an 08:00 start and a 12:00 finish. • Suppliers only need to attend one of the site visits (either Tuesday 25th May 2021 or Wednesday 26th May 2021). • Appointments for site visits must be made by the supplier communicating their required date by using the Bravo Solution messaging function. Full details regarding the site visit and access to the relating tender can be found via Bravo solutions. https://wmca.bravosolution.co.uk/web/login.html Additional information: Please note that all correspondence must be done via the messaging function with Bravo Solutions only. https://wmca.bravosolution.co.uk/web/login.html
Timeline
- Completed: Award date7 October 2021
- Completed: Contract expiry date6 January 2022
- Completed: Award published14 January 2022Current notice
About the buyer
West Midlands Combined Authority is a public sector buyer in United Kingdom publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.
Relevant CPV codes
- 60200000 · Railway transport services
- 71300000 · Engineering services
Decision makers
Connect with the people behind this procurement.
| Contact name | Job title | Phone number | Work email |
|---|---|---|---|
| Head of Procurement | +44 •••• •••••• | ••••••••@west-midlands-combined-authority.gov | |
| Commercial Director | +44 •••• •••••• | ••••••••@west-midlands-combined-authority.gov | |
| Procurement Manager | +44 •••• •••••• | ••••••••@west-midlands-combined-authority.gov | |
| Category Lead | +44 •••• •••••• | ••••••••@west-midlands-combined-authority.gov | |
| Senior Buyer | +44 •••• •••••• | ••••••••@west-midlands-combined-authority.gov | |
| Contracts Manager | +44 •••• •••••• | ••••••••@west-midlands-combined-authority.gov |
25 similar open tenders
See more open tenders related to Bilston and Crescent Rail Replacement.
- Open tender
Property QUDM
- Open tender
DPS for Interim Remediation Works
- Open tender
DPS 2025 - Integrated Design Team
Related buyers
Buyers similar to West Midlands Combined Authority.
- 1,090£989.2m
- 910£690.9m
- 874£1.7bn
- 805£14.1bn
- 759£154.4m
- 735£1.1bn
- 670£1.4bn
- 578£22.6bn
- 549£2.9bn
- 539£267.8m
Win more public sector contracts
Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.