The N69 Listowel Bypass consists of 3.65km of offline road construction as well as the online upgrade of 2.30km of an existing section of urban road.
Details
- Buyer
- Kerry County Council
- Supplier(s)
- Wills Bros
- Topic
- Engineering works and construction works
- Published
- 20 April 2022
- Source
- ie:e_tenders
Tender description
The proposed N69 Listowel Bypass consists of both new, offline road construction as well as the online upgrade of an existing section of urban road, the John B. Keane Road section of the R553/N69. The new, offline section will consist of a single carriageway road situated to the west of the town, approximately 3.65km in length. The online upgrade of the existing John B. Keane Road section of the R553/N69 is approximately 2.30km in length. The existing John B. Keane Road section of the R553 will be re-classified as the N69 upon completion of the scheme. In total, the development is 5.95km in length. Specific elements of the scheme include, but are not limited to; • 3 no. new roundabout junctions and associated improvements to regional and local roads; • Provision of 19 no. structures including a new bridge spanning the River Feale, tied sheet pile wall, accommodation underpasses, flood culverts and watercourse crossings; • Urban realm improvements and an upgrade of vulnerable road user facilities on John B. Keane Road; • Working within, and adjacent to, designated areas; and • All other aspects of road design including site clearance, drainage, earthworks, pavement, safety barriers, signing and lining, public lighting, utilities diversions, fencing and boundary treatments, accommodation works and landscaping. Lot 215957: The N69 Listowel Bypass consists of 3.65km of offline road construction as well as the online upgrade of 2.30km of an existing section of urban road. Tender process for construction of the N69 Listowel Bypass
Timeline
- Completed: Award published20 April 2022Current notice
- Completed: Award date20 April 2022
About the buyer
Kerry County Council is a public sector buyer in Ireland publishing tenders and awards on Stotles. Explore their procurement activity and find more opportunities like this one.
Relevant CPV codes
- 45220000 · Engineering works and construction works
- 45221100 · Construction work for bridges
- 45221110 · Bridge construction work
- 45221111 · Road bridge construction work
- 45233000 · Construction, foundation and surface works for highways, roads
- 45233100 · Construction work for highways, roads
- 45233120 · Road construction works
Decision makers
Connect with the people behind this procurement.
| Contact name | Job title | Phone number | Work email |
|---|---|---|---|
| Head of Procurement | +44 •••• •••••• | ••••••••@kerry-county-council.gov | |
| Commercial Director | +44 •••• •••••• | ••••••••@kerry-county-council.gov | |
| Procurement Manager | +44 •••• •••••• | ••••••••@kerry-county-council.gov | |
| Category Lead | +44 •••• •••••• | ••••••••@kerry-county-council.gov | |
| Senior Buyer | +44 •••• •••••• | ••••••••@kerry-county-council.gov | |
| Contracts Manager | +44 •••• •••••• | ••••••••@kerry-county-council.gov |
26 similar open tenders
See more open tenders related to The N69 Listowel Bypass consists of 3.65km of offline road construction as well as the online upgrade of 2.30km of an existing section of urban road..
Related topics
Topics related to The N69 Listowel Bypass consists of 3.65km of offline road construction as well as the online upgrade of 2.30km of an existing section of urban road., ranked by notice volume.
- 8,426£973.7bn
- 1,745£636.1bn
Win more public sector contracts
Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.